News Flash

Mossy Oaks Stormwater Project Updates

Posted on: January 22, 2021

Mossy Oaks update through Jan. 29

Jan. 22, 2020

Ladies and Gentlemen:

Please see the two maps that detail work through Jan. 29 in Basin 1 (vicinity of the Duck Pond) and Basin 2 (vicinity of Southside Park). 

Basin 1

Despite the rain and colder weather, progress was made this week. The Spanish Moss Trail was prepared for concrete installation and the first 250 feet has been poured. We expect it will take about four full days to repave the trail. Many new concrete sidewalks have been poured along Battery Creek Road and First Blvd. Next week, cleanup and concrete work continues on the Spanish Moss Trail, Battery Creek Road and First Blvd. We are still awaiting delivery of the pipe that will be installed between homes from North Royal Oaks to Battery Creek Road.


Basin 1 through Jan. 29

Basin 2

As advertised, the contractor returned to the Lawton Farms Road area to complete finishing work. The contractor expects to work this weekend to resolve the remainder of the minor but outstanding issues. With regard to the Spanish Moss Trail between Riverside Drive and Brotherhood Lane, all three headwalls have been installed. This sets the stage to attach the massive drainpipes and install the three flap gates. Following the installation of the flap gates, the Spanish Moss Trail will be repaved and reopened. We are not expecting to work this weekend.

Basin 2 thru Jan. 22

Safety!

We’ve had another perfect week of safety. Thanks to all who have worked so hard to ensure we maintain a safe environment.          

Stay informed

I’m available anytime to address your questions comments or concerns. No issue is too big or too small, so please don’t hesitate to reach out anytime. 

This project remains on-time and on-budget.     

Have a fantastic weekend.

Neal Pugliese, Col USMC (Ret)
Chairman
Mossy Oaks Multijurisdictional Drainage Task Force
npugliese@cityofbeaufort.org
843-470-3512

Facebook Twitter Email

Other News in Mossy Oaks Stormwater Project Updates

Mossy Oaks update through March 26

Posted on: March 19, 2021

Mossy Oaks update through March 5

Posted on: February 26, 2021

Mossy Oaks update through Feb. 28

Posted on: February 19, 2021

Mossy Oaks update through Feb. 19

Posted on: February 12, 2021

Mossy Oaks update through Feb. 12

Posted on: February 5, 2021

Mossy Oaks update through Feb. 5

Posted on: January 29, 2021

Mossy Oaks update through Jan. 22

Posted on: January 14, 2021

Mossy Oaks update through Jan. 13

Posted on: January 8, 2021

Mossy Oaks update through Jan. 8

Posted on: December 30, 2020

Mossy Oaks update through Jan. 4

Posted on: December 23, 2020

Mossy Oaks update through Dec. 25

Posted on: December 17, 2020

Mossy Oaks update through Dec. 18

Posted on: December 11, 2020

Mossy Oaks update through Dec. 11

Posted on: December 4, 2020

Water service interruption on Dec. 8

Posted on: December 4, 2020

Mossy Oaks update through Dec. 4

Posted on: November 25, 2020

Mossy Oaks update through Nov. 27

Posted on: November 19, 2020

Mossy Oaks update through Nov. 13

Posted on: November 6, 2020

Mossy Oaks update through Nov. 6

Posted on: October 30, 2020

Mossy Oaks update through Oct. 30

Posted on: October 23, 2020

Mossy Oaks update Oct. 13-23

Posted on: October 14, 2020

Mossy Oaks update Oct. 6-16

Posted on: October 9, 2020

Mossy Oaks update Sept. 29-Oct. 9

Posted on: October 2, 2020

Mossy Oaks update Sept. 22-Oct. 2

Posted on: September 25, 2020

Mossy Oaks update Sept. 15-25

Posted on: September 17, 2020

Mossy Oaks updates: July 21-31

Posted on: July 22, 2020